Stage 1 estimate
FRSA's October 2025 charter estimated construction at $50–70 million. It described this as an early estimate including escalation and contingency.
P10 · Funding
FRSA's project charter lists what it needs for a Stage 1 investment decision.
FRSA's stated requirements
Detailed Stage 1 costs and a timetable, civil designs and Shire approvals, and progress on construction tenders. For funding, FRSA lists donations and pledges, a contract to sell its Armadale school property (subject to conditions), and in-principle debt support.
FRSA's stated target
FRSA’s landing page, checked on 27 October 2026, still refers to September 2026 without stating an outcome. The target concerned FRSA’s own decision to invest. Construction depends on separate planning, approval-condition and permit steps.
Evidence basis: FRSA's October 2025 Project Charter and Scope, executive summary and section 10.2, for the Stage 1 estimate and decision requirements; its Oakford pledge form for the fundraising estimate; and its Oakford project page for the stated decision month. The charter sets out FRSA's own requirements; it does not establish their completion. The landing page was checked on 27 October 2026. This focused check did not revalidate every finance source or establish whether an internal decision occurred.