Stage 1 estimate
FRSA's October 2025 charter estimated construction at $50–70 million. It described this as an early estimate including escalation and contingency.
P10 · Funding
FRSA's project charter lists what it needs for a Stage 1 investment decision.
FRSA's stated requirements
Detailed Stage 1 costs and a timetable, civil designs and Shire approvals, and progress on construction tenders. For funding, FRSA lists donations and pledges, a contract to sell its Armadale school property (subject to conditions), and in-principle debt support.
FRSA's stated target
The target concerns FRSA's own decision to invest. Construction depends on separate planning, approval-condition and permit steps.
Evidence basis: FRSA's October 2025 Project Charter and Scope, executive summary and section 10.2, for the Stage 1 estimate and decision requirements; its Oakford pledge form for the fundraising estimate; and its Oakford project page for the stated decision month. The charter sets out FRSA's own requirements; it does not establish their completion.