Evidence baseline: 30 September 2026This is a dated publication, not a live feed.
Oakford Campus Public RecordEvidence, context and current position

P06–P09 · Roads, water and services

The project depends on infrastructure beyond the site.

Roads, water and services remain part of the delivery picture.

The permanent roundabout, the required Abernethy Road footpath, groundwater and private service connections each affect when and how the campus could proceed.

Permanent roundabout

Required before the school can operate

Condition Q requires approved plans and full construction before school operations begin. The Shire currently sequences the permanent roundabout after completion of the Tonkin Highway Extension.

Open roundabout explainer →

Abernethy Road footpath

A footpath must connect the site to the Tonkin Hwy PSP

Condition R requires approved plans before a Building Permit is issued and construction by FRSA before school operations begin.

Open footpath explainer →

Groundwater

An allocation exists; the supply is not yet demonstrated

FRSA holds a 17,250 kL annual allocation from the Superficial Swan aquifer. The licence alone does not establish bore yield, water quality, seasonal reliability or the complete campus water system.

Open water explainer →

Service connections

The servicing pathway is not yet clear

The public record does not establish the proposed routes, approvals, levels or costs for water, wastewater, power and communications. That uncertainty does not establish that servicing is impossible.

Open services explainer →