Evidence baseline: 30 September 2026This is a dated publication, not a live feed.
Oakford Campus Public RecordEvidence, context and current position

P11 · What happens next

What would clarify the proposal’s next stage?

FRSA has targeted September 2026 for its Stage 1 investment decision. The design it ultimately pursues, its planning pathway, approval requirements and infrastructure arrangements remain separate matters to track.

In short

What would change the public position

See the milestone watchlist

These entries track different decisions and stages. Their order is not a construction timetable, and a missing public record does not establish that a step has not occurred.

MilestoneWhy it mattersPosition in the reviewed record
Design and planning pathwayWhich plans FRSA pursues, whether the existing approval covers them, and whether a further decision is required.May 2026 design published; its pathway is not established in the reviewed record.
Stage 1 investment decisionFRSA's charter calls for Oakford Delivery Team, Board and Association approval. Its FID requirements include cost and programme detail, tender progress, fundraising, a JCCC sale contract and in-principle debt support.No outcome is established in the sources reviewed for this edition.
Condition decisions and civil approvalsThe operative Conditions have different timing, including requirements before development starts, Building Permit lodgement or issue, and school operations.No complete public clearance register is available.
Service arrangementsWater, wastewater, stormwater, power and fire-service requirements need to be addressed as the proposal advances.A groundwater allocation is documented; final service arrangements are not established here.
Roundabout and footpathCondition Q requires Shire-approved roundabout plans before Building Permit lodgement; Condition R requires Shire-approved footpath plans before permit issue. Both works must be built before school operations. Condition Q also requires contribution arrangements.Post-Tonkin roundabout sequencing is published; plan approvals and contribution arrangements are not established in the evidence baseline.
Condition P land arrangementsSatisfactory arrangements to cede the corner land are a separate approval-condition question.Strong indication of excision; formal Condition P clearance not established.
Building PermitA separate legal step for proposed building works, after the Conditions tied to lodgement and issue have been addressed.Issue not established in the reviewed record.

Evidence basis: FRSA's October 2025 Project Charter and Scope, sections 10 and 13, for its FID requirements and Association decision process; operative Conditions A–T for the differing trigger points; FRSA's May 2026 masterplan and the design comparison; and the roads and water record for the documented infrastructure position. Status descriptions reflect the evidence review completed on 30 September 2026, including the author’s manual checks, not a live approvals register.