P11 · What happens next
What would clarify the proposal’s next stage?
FRSA targeted September 2026 for its Stage 1 investment decision. That target month has passed. FRSA’s landing page, checked on 27 October 2026, still refers to September 2026 without stating an outcome. The design it ultimately pursues, its planning pathway, approval requirements and infrastructure arrangements remain separate matters to track.
In short
What would change the public position
- Design and planning pathway. Identification of the plans FRSA intends to pursue and whether they can proceed under the existing approval or need a further planning decision.
- FRSA decisions. A disclosed outcome of its stated Stage 1 Final Investment Decision and Association approval process. An internal decision does not itself grant statutory approval.
- Conditions and commencement. Evidence that requirements applying before development commences have been addressed, with Building Permit lodgement and issue requirements tracked at their own trigger points.
- Services and roads. Documented servicing arrangements and Shire-approved roundabout and footpath plans, with the required works tracked separately before school operations.
See the milestone watchlist
These entries track different decisions and stages. Their order is not a construction timetable, and a missing public record does not establish that a step has not occurred.
| Milestone | Why it matters | Position in the reviewed record |
|---|---|---|
| Design and planning pathway | Which plans FRSA pursues, whether the existing approval covers them, and whether a further decision is required. | May 2026 design published; its pathway is not established in the reviewed record. |
| Stage 1 investment decision | FRSA's charter calls for Oakford Delivery Team, Board and Association approval. Its FID requirements include cost and programme detail, tender progress, fundraising, a JCCC sale contract and in-principle debt support. | September 2026 was FRSA’s stated target month. The landing page checked on 27 October still refers to that month without stating an outcome. An internal decision is not established by this check. |
| Condition decisions and civil approvals | The operative Conditions have different timing, including requirements before development starts, Building Permit lodgement or issue, and school operations. | No complete public clearance register is available. |
| Service arrangements | Water, wastewater, stormwater, power and fire-service requirements need to be addressed as the proposal advances. | A groundwater allocation is documented; final service arrangements are not established here. |
| Roundabout and footpath | Condition Q requires Shire-approved roundabout plans before Building Permit lodgement; Condition R requires Shire-approved footpath plans before permit issue. Both works must be built before school operations. Condition Q also requires contribution arrangements. | Post-Tonkin roundabout sequencing is published; plan approvals and contribution arrangements are not established in the evidence baseline. |
| Condition P land arrangements | Satisfactory arrangements to cede the corner land are a separate approval-condition question. | Strong indication of excision; formal Condition P clearance not established. |
| Building Permit | A separate legal step for proposed building works, after the Conditions tied to lodgement and issue have been addressed. | Issue not established in the reviewed record. |
Evidence basis: FRSA's October 2025 Project Charter and Scope, sections 10 and 13, for its FID requirements and Association decision process; operative Conditions A–T for the differing trigger points; FRSA's May 2026 masterplan and the design comparison; and the roads and water record for the documented infrastructure position. Status descriptions reflect the evidence review completed on 30 September 2026, including the author’s manual checks, not a live approvals register. The FRSA landing page was checked on 27 October 2026 and still states no FID outcome. This was not a fresh review of every source. The roads record incorporates the separately dated October updates.