Evidence baseline: 30 September 2026This is a dated publication, not a live feed.
Oakford Campus Public RecordEvidence, context and current position

P07 · Kargotich Road and Abernethy Road

The permanent roundabout is still required.

The Shire's current public programme sequences its delivery after completion of the Tonkin Highway Extension.

Main Roads presently expects the Extension to be completed in late 2028.

In short

What the public record shows

See why the work is sequenced this way

The Shire's documents indicate that constructing the permanent roundabout will require the intersection to be closed for at least four months. Its current public programme sequences that work after the Tonkin Highway Extension, avoiding an overlapping extended closure while major network works are under way. This establishes the published sequence, rather than proving that earlier construction would be legally or physically impossible.

  1. 1

    Approval basis

    The traffic assessment relied on a permanent roundabout being completed before school operations began.

  2. 2

    Condition Q

    Condition Q requires approved plans, full construction before school operations and satisfactory funding arrangements for an FRSA full or partial contribution determined by the Shire.

  3. 3

    Tonkin Highway works

    Tonkin Highway construction affects traffic, haulage, road levels and the surrounding network through the programme period.

  4. 4

    Funding retained

    The Shire says $8.25 million has been retained for the permanent roundabout once the Tonkin Highway Extension is complete.

  5. 5

    Current programme

    Main Roads presently expects the Tonkin Highway Extension to be completed in late 2028. The Shire's current programme places permanent-roundabout construction after the Extension.

What remains unresolved publicly

Evidence basis: Operative Conditions P and Q; SAT order; current cadastral mapping for Lot 162 on Deposited Plan 429870; dated local observations and THETRU communications concerning the temporary treatment; CPS 10600/2 supporting memorandum and DWER application directory; Shire road-upgrade announcement, 2 July 2026; Main Roads Tonkin Highway Extension project page. Cadastral and application records are not substituted for formal Condition P clearance or an issued CPS 10600/2 decision. Programme dates remain time-sensitive.