Oakford Campus Public RecordEvidence, context and current position

P09 · Service connections

The 2023 servicing report outlines possible connections along Abernethy Road.

A proposed water-main extension and an optional sewer connection would need to account for existing drains and the future Tonkin Highway corridor. Their final designs are not established by the reviewed material.

In short

What the public record shows

Related corridor works

The preliminary routes raise a coordination question

The 2023 report identifies road reserves, existing services, vegetation, drains, bridges and culverts, and the future Tonkin Highway reserve as design considerations for possible off-site mains. Main Roads describes an Abernethy Road underpass and a principal shared path. These sources do not establish a physical clash within one narrow strip.

See the 2023 servicing options

Potable water

The report proposed extending a water main approximately 2.5 km along Abernethy Road from Tourmaline Boulevard. It identified the future Tonkin Highway reserve and drainage crossings as design considerations, not a final approved alignment.

Wastewater

The report examined a private pressure main of approximately 3.2 km to Byford and on-site effluent disposal as possible solutions. The off-site route is not established as the selected solution; Condition F addresses approval of a sewage-treatment and disposal apparatus.

Power

The report identified a nearby high-voltage network, but said the feeder extension and any reinforcement required Western Power assessment. It did not establish a route through this road interface.

Communications

The report considered fixed wireless service and a possible fibre extension if fixed-line service were needed. Its network observations date from 2023 and require current confirmation.

What remains unclear from the available record

Evidence basis: JDSi's 2023 Engineering Servicing Report, sections 5–9 (Appendix K to the campus proposal in the Shire's application archive); operative Condition F and Condition R; FRSA's October 2025 Project Charter and Scope, section 6.5; Main Roads Tonkin Highway Extension project page. The 2023 servicing report is preliminary and does not establish the design now proposed or approved.